| Table 3 |
| FY 2000 Funding for New Start Projects |
|
(Millions of Dollars) |
| |
|
|
|
|
|
|
|
| |
|
FY 1998 and |
|
FY 2000 |
Remaining |
Total |
| |
|
Prior Year Earmarks |
FY 1999 |
Recommended |
FFGA |
Recommended |
| City/Project |
Overall Project Rating |
Obligated |
Unobligated |
Earmarks |
Funding |
Funding |
Funding |
| EXISTING FULL FUNDING GRANT AGREEMENTS |
|
|
|
|
|
|
|
|
| Atlanta - North Line Extension |
FFGA |
$208.15 |
$0.00 |
$51.72 |
$45.14 |
FFGA Complete |
$305.01 |
|
| Boston - Piers Transitway Phase 1 |
FFGA |
142.20 |
46.10 |
53.58 |
53.96 |
34.89 |
330.73 |
|
| Denver - Southwest LRT |
FFGA |
25.76 |
0.00 |
39.70 |
35.00 |
19.54 |
120.00 |
|
| Houston - Regional Bus Plan |
FFGA |
287.02 |
91.24 |
59.23 |
62.52 |
FFGA Complete |
499.99 |
|
| Los Angeles - MOS -3 Segments of Metro Rail |
FFGA |
547.62 |
23.91 |
37.72 |
50.00 |
757.24 |
1,416.49 |
|
| Maryland - MARC Extensions - Point of Rocks to Frederick |
FFGA |
120.89 |
0.00 |
16.91 |
0.70 |
FFGA Complete |
138.51 |
1 |
| Northern New Jersey - Hudson-Bergen LRT |
FFGA |
158.82 |
0.00 |
69.48 |
99.00 |
276.78 |
604.08 |
|
| Portland - Westside LRT |
FFGA |
593.48 |
0.00 |
25.53 |
11.06 |
FFGA Complete |
630.07 |
|
| Sacramento - South Corridor LRT |
FFGA |
30.15 |
0.00 |
23.31 |
25.00 |
34.72 |
113.18 |
1 |
| Salt Lake City - South LRT |
FFGA |
136.59 |
0.00 |
69.48 |
37.93 |
FFGA Complete |
243.99 |
1 |
| San Francisco - BART to Airport |
FFGA |
113.73 |
0.00 |
39.70 |
84.00 |
512.57 |
750.00 |
|
| San Jose - Tasman LRT |
FFGA |
124.08 |
0.00 |
26.80 |
31.87 |
FFGA Complete |
182.75 |
|
| San Juan - Tren Urbano |
FFGA |
33.38 |
0.00 |
19.85 |
82.00 |
177.14 |
312.37 |
1 |
| St. Louis - St. Clair County, Illinois LRT |
FFGA |
78.09 |
0.00 |
34.74 |
50.00 |
89.58 |
252.41 |
1 |
| SUBTOTAL |
|
$2,599.95 |
$161.25 |
$567.74 |
$668.18 |
$1,902.47 |
$5,899.58 |
|
| |
|
|
|
|
|
|
|
|
| PROPOSED FULL FUNDING GRANT AGREEMENTS |
|
|
|
|
|
|
|
|
| Dallas - North Central LRT Extension |
Recommended |
$16.36 |
$10.96 |
$15.88 |
$70.00 |
|
|
|
| Fort Lauderdale - Tri-Rail Commuter Rail Upgrade |
Highly Recommended |
51.29 |
0.00 |
3.97 |
20.00 |
|
|
|
| Memphis - Medical Center Extension |
Recommended |
5.75 |
0.00 |
2.18 |
15.11 |
|
|
|
| Newark Rail Link (MOS-1) |
Highly Recommended |
11.95 |
0.00 |
5.96 |
12.00 |
|
|
|
| Orlando - I-4 Central Florida LRT Project |
Highly Recommended |
24.59 |
9.10 |
17.37 |
44.00 |
|
|
|
| Salt Lake City - Downtown Connector |
Not Recommended |
0.00 |
0.00 |
4.96 |
20.00 |
|
|
|
| San Diego - Mission Valley East LRT Extension |
Highly Recommended |
0.00 |
1.00 |
1.49 |
35.00 |
|
|
|
| SUBTOTAL |
|
$109.94 |
$21.06 |
$51.81 |
$216.11 |
|
|
|
| |
|
|
|
|
|
|
|
|
| OTHER PROJECTS IN FINAL DESIGN |
|
|
|
|
|
|
|
|
| Dallas - Ft. Worth - RAILTRAN Phase 2 |
Recommended |
$11.39 |
$23.11 |
$11.91 |
$0.00 |
|
|
|
| Los Angeles - LOSSAN Rail Corridor Improvement Project |
Not Recommended |
19.89 |
0.00 |
0.00 |
0.00 |
|
|
|
| New Orleans - Canal Streetcar Spine |
Not Recommended |
18.44 |
13.93 |
21.84 |
0.00 |
|
|
|
| Tacoma-Seattle (Sounder) Commuter Rail |
Recommended |
5.83 |
8.97 |
40.69 |
0.00 |
|
|
|
| SUBTOTAL |
|
$55.54 |
$46.01 |
$74.44 |
$0.00 |
|
|
|
| |
|
|
|
|
|
|
|
|
| PRELIMINARY ENGINEERING |
|
|
|
|
|
|
|
|
| Baltimore - Central Corridor LRT Double Track |
Recommended |
$0.00 |
$0.00 |
$0.99 |
$8.00 |
|
|
|
| Minneapolis - Hiawatha Corridor Transitway |
Recommended |
1.50 |
10.46 |
16.87 |
8.00 |
|
|
|
| Raleigh-Durham - Research Triangle Regional Rail |
Recommended |
1.29 |
12.66 |
9.93 |
8.00 |
|
|
|
| Seattle-Sound Move - Link LRT |
Highly Recommended |
0.00 |
11.95 |
4.96 |
8.00 |
|
|
|
| Available For Other Projects |
|
|
|
|
46.43 |
|
|
|
| Austin - Northwes/North Central Corridor |
Not Rated |
$0.00 |
$1.00 |
$0.99 |
|
|
|
|
| Boston - Piers Transitway Phase 2 |
Not Recommended |
0.00 |
0.00 |
0.00 |
|
|
|
|
| Chicago - Central Kane Corridor |
Recommended |
1.00 |
0.00 |
1.99 |
|
|
|
|
| Chicago - North Central Corridor |
Not Recommended |
1.00 |
0.00 |
1.99 |
|
|
|
|
| Chicago - Southwest Corridor |
Highly Recommended |
1.00 |
0.00 |
1.99 |
|
|
|
|
| Cincinnati - NE/I-71 |
Not Recommended |
6.50 |
0.50 |
1.79 |
|
|
|
|
| Cleveland - Euclid Corridor |
Not Recommended |
6.52 |
0.00 |
1.99 |
|
|
|
|
| Denver - Southeast Corridor |
Not Recommended |
0.00 |
0.00 |
0.50 |
|
|
|
|
| Kansas City - Southtown LRT |
Not Recommended |
4.02 |
0.00 |
0.00 |
|
|
|
|
| Las Vegas - Resort Corridor |
Not Recommended |
0.00 |
4.98 |
3.97 |
|
|
|
|
| Little Rock - Junction Bridge/River Rail |
Not Recommended |
0.18 |
1.81 |
0.99 |
|
|
|
|
| Miami - East/West Corridor |
Not Recommended |
0.00 |
6.47 |
2.98 |
|
|
|
|
| Miami - North 27th Avenue Corridor |
Not Recommended |
2.97 |
5.97 |
2.98 |
|
|
|
|
| New York City - LIRR East Side Access |
Not Recommended |
0.00 |
19.94 |
23.82 |
|
|
|
|
| N. New Jersey (Hudson-Bergen MOS-2) |
Not Rated |
0.00 |
0.00 |
0.00 |
|
|
|
|
| Norfolk - Virginia Beach Cooridor |
Not Recommended |
0.00 |
1.99 |
7.94 |
|
|
|
|
| Orange County - Irvine-Fullerton Corridor |
Recommended |
4.97 |
0.00 |
2.48 |
|
|
|
|
| Phoenix - Central Phoenix/East Valley |
Not Recommended |
0.00 |
3.99 |
4.96 |
|
|
|
|
| Pittsburgh - Martin Luther King, Jr. E. Busway Extension |
Not Recommended |
0.00 |
0.00 |
0.00 |
|
|
|
|
| Pittsburgh - Stage II LRT Reconstruction |
Not Recommended |
0.00 |
0.00 |
3.97 |
|
|
|
|
| Portland - South/North Cooridor |
Not Recommended |
5.96 |
0.00 |
0.00 |
|
|
|
|
| San Diego - Mid Coast Corridor |
Highly Recommended |
1.45 |
2.99 |
1.99 |
|
|
|
|
| San Diego - Oceanside Escondido Corridor |
Highly Recommended |
0.00 |
2.99 |
2.98 |
|
|
|
|
| San Francisco - Bayshore - Third Street LRT |
Recommended |
0.00 |
0.00 |
0.00 |
|
|
|
|
| San Juan - Minillas Extension |
Not Rated |
0.00 |
0.00 |
0.00 |
|
|
|
|
| Tampa - Tampa Regional Rail |
Not Recommended |
3.97 |
0.00 |
0.99 |
|
|
|
|
| Washington DC - Largo Extension |
Recommended |
0.00 |
0.00 |
0.99 |
|
|
|
|
| SUBTOTAL |
|
$42.32 |
$87.70 |
$105.01 |
$78.43 |
|
|
|
| |
|
|
|
|
|
|
|
|
| TOTAL |
|
$2,807.75 |
$316.02 |
$799.01 |
$962.72 |
$1,902.47 |
$5,899.58 |
|
| Additional FY1999 Earmarks |
|
|
|
97.02 |
|
|
|
|
| Ferry Capital Projects (AK or HI) (Section 5309(m)(5)(A)) |
|
|
|
|
10.32 |
|
|
|
| Oversight Activities |
|
|
|
6.77 |
7.35 |
|
|
|
| GRAND TOTAL |
|
$2,807.75 |
$316.02 |
$902.80 |
$980.40 |
$1,902.47 |
$5,899.58 |
|
| |
|
|
|
|
|
|
|
|
| Note: Totals may not add due to rounding. |
|
| |
| 1) Totals include prior year funding not included in FFGA. See Text. |