Section 3035 (tt) of ISTEA required FTA to negotiate and sign a multi-year grant agreement for the North Line extension from Medical Center to North Springs.
FTA awarded $92.49 million for final design and construction of the segment from Medical Center through the Dunwoody Station in 1991 and 1992.
In December 1994, MARTA and FTA entered into a Full Funding Grant Agreement (FFGA) in the amount of $305.01 million (Section 5309 New Start funds) for the extension from Dunwoody through North Springs. Through FY 1997, Congress has appropriated $163.63 million in Section 5309 New Start funds for this project.
The original total estimated cost for this extension as reflected in the FFGA was $381.3 million and included the purchase of 28 rail vehicles. Due to changed conditions, recent scope enhancements and additional rail car requirements, the total project cost is currently estimated at $490.6 million. The expanded scope requirements are due to increases in estimated service levels, station parking enhancements, and rights-of-way impacts stemming from widening of the adjacent GA 400 freeway. As specified in the FFGA, any costs exceeding the $381.3 million cap are to be derived from non-Federal sources. |