|
1. Overview
Alternatives to traditional low bid procurement are increasingly being pursued by public agencies that want to ensure successful, fast-track implementation of major projects. Next to the RFP process, design-build may be the most common method of negotiated procurement. Tri-Met has used a third method of non-traditional procurement called Construction Manager/General Contractor (CM/GC) to construct light rail facilities. Not as well understood as other methods, it is not as frequently used. Depending upon location, there may be legal obstacles to its implementation.
2. Background
CM/GC is a middle ground negotiated procurement method. Several of the features of Tri-Met’s program help define this contracting approach:
- Contractor is selected during the design process and provides value engineering and constructibility reviews; CM/GC contractor is not responsible for final design, however, the selection is based several evaluation criteria, such as technical and management experience; prior performance; safety record; proposed quality control plan; proposed community outreach, including disadvantaged business participation and workforce hiring/training programs; and, maximum percentage fee on construction value. Lowest construction price is not a selection criterion.
- Contractor assumes responsibility for the entire construction package with a dual role as the construction manager for all project work, self-performed and subcontracted, and the general contractor, soliciting bids from and executing contracts with subcontractors. The owner contracts only with the CM/GC contractor.
- Subcontracted work is competitively obtained, primarily as low bid.
- Construction price is negotiated once final design is complete; contractor and owner agree on a Guaranteed Maximum Price (GMP) for the contract package.
Before awarding CM/GC or other non-traditional construction contracts, Tri-Met’s must demonstrate the rationale for procuring work through non-low bid methods. Under Oregon law, a public hearing must be held. An exemption from competitive bidding is allowed if the public agency finds (a) the contract award would be unbiased and not encourage favoritism and (b) substantial cost savings are likely.
Portland Tri-Met adopted CM/GC extensively to construct its $350 million Interstate MAX light rail line. Approximately $110 million of a $235 million construction program is under CM/GC contracts.
3. Lessons
With the Interstate MAX project still in construction and major contract closeouts not anticipated much before revenue service begins in 2004, the lessons learned from the CM/GC contracting method are not complete. The most important lesson is likely to be the effect on bottom line project cost. Several important findings midway through construction include:
- Legal authority must exist for agencies to pursue alternative contracting (i.e., non-low bid) methods. In Oregon, existing legislation enables public agencies to procure construction contracts using CM/GC, design-build, and the RFP process basing selection on multiple factors. Tri-Met adopted CM/GC for two major contracts.
- Awarding CM/GC contracts prior to start of construction allows for valuable contractor input during final design in the form of constructibility reviews and second party cost estimates. Tri-Met found the assistance invaluable for reconciling conflicting capital cost estimates and in value engineering practicable cost savings that would keep Interstate MAX within the $350 million budget.
- Establishing a Guaranteed Maximum Price (GMP) with the CM/GC contractor before construction actually begins provides greater certainty about the final project costs. Typically many quantities and work elements are negotiated as lump sum costs and only if there are significant changes in design or scope occur would these prices change. Change orders are still allowed under the CM/GC contract but are expected to be fewer and lower cost on average. Reducing the owner’s claims risk was especially important for Interstate MAX where the construction budget was constrained and costly claims during the course of a contract would threaten Tri-Met’s ability to complete the project as planned.
- If the project owner and CM/GC contractor cannot agree on a GMP, the owner retains the option to seek alternative bids. This provides one level of owner leverage over the contractor when negotiating construction costs. Tri-Met did not see the need for such recourse, concluding that the contractors’ prices were reasonable.
- Competitive bidding of subcontractor work elements, which are under the contract management of the CM/GC contractor, is another level of control on contractor pricing and provides an indicator, albeit indirect, of construction market conditions. These CM/GC-subcontract relationships are open to review by the project owner. In negotiating the GMPs for the two Interstate MAX CM/GC contracts, Tri-Met was able to inspect contractor pricing data, including subcontracted items. Tri-Met also had control of pricing through the development and approval of contracting plans that identified what work would be self-performed and what work would be subcontracted by the CM/GC contractor. These plans are intended to allocate work to the most capable, available firms, thereby controlling not just the overall price but also the work schedule, quality, safety management, and community impacts.
- Tri-Met’s experience is the CM/GC method fosters teamwork and promotes the formation of non-adversarial relationships. This partnership between the contractor and project owner has intangible benefits. A better understanding of the project scope and objectives should lead to a more flexible, responsive contractor. As a result, the owner can be more responsive to community concerns during the construction period. The level of construction activity can be modified to conform to changing needs. For instance, because a single CM/GC contractor was responsible for the entire section of work in the urbanized portion of Interstate MAX, activity in business districts was avoided or minimized during critical periods (e.g., the peak Christmas shopping season, the primary business hours) and temporarily focused elsewhere.
- With a more cooperative working partnership between the owner, the designer and CM/GC contractor—Tri-Met calls these entities the CM/GC team—work quality should improve. The contractor has been selected on factors other than just price, many of which are strong indicators of ability to complete the job successfully. Also, the CM/GC contractor has increased responsibility for quality control over all aspects of the job under this method.
- The approach is not without potential disadvantages, including the fact that the owner has less leverage over the contractor when pricing construction activities since there are no other competitors at this point. The owner may not have available complete information on construction market conditions, information that is otherwise revealed through the competitive bidding process. Tri-Met, fortunately, had recent bid histories on many similar work items from the Westside-Hillsboro project and could obtain additional information from the Portland Streetcar and Airport MAX construction programs. In accordance with the terms of the contracting plan, the CM/GC contractor obtained low bids for certain segments of work. Tri-Met could have requested that the contractor obtain bids for additional work items but concluded that was not necessary.
- The performance to date of Tri-Met’s two major CM/GC contracts for the Interstate MAX light rail line is exemplary from the perspective of keeping the project on schedule and maintaining good quality but mixed from a budget standpoint.
- The negotiated GMPs ended up significantly above the owner’s design engineers’ cost estimates, upwards of 15 to 20 percent depending upon the time the estimates were prepared (e.g., 60 percent and 95 percent of final design). Tri-Met concluded, however, that the contractors’ cost estimates were accurate and reasonable when quantities were reconciled and other oversights in the engineers’ designs and cost estimates were corrected. Tri-Met independently reconciled its final cost estimate with that of the CM/GC contractor. The negotiated GMP was actually less than Tri-Met’s final estimate and within the contingency allowance of earlier estimates.
- Change order trends through a year’s worth of construction are positive, with owner-directed changes running under 3 percent of the GMP construction cost. Tri-Met is forecasting the project to come in at or under budget in large part due to the benefits of CM/GC. Should this trend continue, the small dollar value of changes will bolster the argument that the CM/GC method helps identify and reconcile price differences in the owner and contractor’s understanding of work scope, technical requirements, quantities, and risk allocation prior to initiating construction.
4. Applicability
CM/GC warrants consideration along with design-build and RFP selection when legal and institution frameworks allow negotiated procurement of construction projects and when CM/GC’s advantages can be best realized. The advantages are having a single contractor responsible for a large share of the work, a contractor who can effectively manage a variety of subcontractors on a complex project. The types of projects where CM/GC is most relevant are those with multiple interfaces (agency, public, business) and high public expectations; where contractor input during design would be useful; and where the owner wants to retain control through final design and to have continuing influence during construction. Both traditional design-bid-build and design-build itself are less well suited for procurement under these circumstances.
The owner must be experienced in construction and have the internal resources to check contractor cost proposals and negotiate a contract with confidence that the agreed upon terms are fair and reasonable.
1 This discussion draws heavily on information provided by Portland Tri-Met. The FTA would like to acknowledge the contributions of Don Iwin, Construction Manager, and Neil McFarlane, Executive Director, Capital Projects and Facilities Division.
5. Contacts
Jeffrey Allen / David Benjamin Parsons Transportation Group 120 Howard Street, Suite 850 San Francisco, CA 94105 (415) 495-6060
Don Irwin / Neil McFarlane Tri-County Metropolitan Transportation District (Tri-Met) 710 N.E. Holladay Street Portland, OR 97232 (503) 239-2132
Michael J. Williams, Region X Federal Transit Administration 915 2nd Avenue, Suite 3142 Seattle, WA 98174 (206) 220-7965
|