You are here:Home Legislation, Regulations & Guidance Circulars/Significant Guidance Full-Funding Grant Agreements Guidance Interim Guidance on Design-Build Project Delivery and the FFGA Process Design-Build and Design-Build-Operate-Maintain Chart

Design-Build and Design-Build-Operate-Maintain Chart


Open printable version in a new window

MILESTONES FOR DESIGN-BUILD PROJECTS

MILESTONES FOR DESIGN-BUILD PROJECTS CHART

1. Grantee requests entry into preliminary engineering (PE)

2. FTA approves project entry into PE

3. Grantee begins process of pre-qualifications for Design-Build/Design-Build-Operate-Maintain (DB/DBOM) firms

4. FTA issues Record of Decision or Finding of No Significant Impact

5. Grantee requests proposals from select DB/DBOM firms

6. FTA approves project entry into final design (FD)

7. FTA issues Letter of No Prejudice (LONP) for specified activities

8. Grantee begins activities authorized under LONP and pre-award authority

9. FTA and grantee begin discussions on Full Funding Grant Agreement (FFGA)

10. FTA prepares financial capacity baseline report

11. Grantee receives final proposals from select DB/DBOM firms

12. Grantee selects the winning proposal

13. FTA prepares financial capacity spot report

14. Final FFGA process begins (i.e., formal submittal, 60 days notification to Congress)

15. FTA awards FFGA

16. Grantee awards contract and gives notice to proceed

Note: In some cases the contract may be awarded and notice to proceed given before an FFGA is signed.




Submit a Question or Suggestion/Issue
Submit a Technical Issue on this page
Home | Related Links | FOIA | DOT.gov | WhiteHouse.gov | USA.gov | OIG Hotline | Regulations.gov | FTA Web Policies | Privacy Policy | No FEAR
Adobe Acrobat Reader | MS Word Viewer | MS Excel Viewer | MS PowerPoint Viewer
Region I Region II Region III Region IV Region V Region VII Region VI Region VIII Region IX Region X Region X Region IX LMRO