FTA's requirements concerning domestic preference for federally funded transit projects are set forth in 49 U.S.C. §5323(j). However, Section 5323(j)(2)(B) states that those requirements shall not apply if the item or items being procured are not produced in the U.S. in sufficient and reasonably available quantities and of a satisfactory quality. The implementing regulation also provides that a waiver may be requested "for a specific item or material that is used in the production of a manufactured product." 49 C.F.R. 661.7(g). The regulations allow a bidder or supplier to request a waiver only if it is being sought under this section. See, 49 C.F.R. 661.7(g) and 49 C.F.R. 661.9(d).
You state that there are no U.S. manufacturers of this component with the same operational and dimensional characteristics. This assertion is supported by a market survey furnished as part of your application and conducted for Toyocom by GFI Genfare, a ticket vending machine manufacturer and potential end user of this component. FTA also posted a request for comments on this matter on our website and received no comments from domestic manufacturers of this product.
Based on the above-referenced information, I have determined that the grounds for a "non-availability" waiver exist. Therefore, pursuant to the provisions of 49 U.S.C. §5323(j)(2)(B), a waiver is hereby granted for manufacture of the Model BV-6000 bill processing unit for a period of two years, or until such time as a domestic source for this type of unit becomes available, whichever occurs first. In order to insure that the public is aware of this waiver, particularly potential manufacturers, it will be published in the Federal Register.
If you have any questions, please contact Joseph Pixley at (202) 366-1936.
Very truly yours,
(Signed)
Gregory B. McBride
Deputy Chief Counsel