Contract No. |
Description |
Cost ($Millions) Escalated* |
|---|---|---|
|
Preliminary engineering |
$ 10.3 |
|
|
Final engineering and project Management |
$ 43.8 |
|
|
Real estate |
$ 7.6 |
|
|
Vehicles |
$ 23.3 |
|
|
Construction Contracts |
||
|
1 |
Maintenance facility and yard |
$ 34.7 |
|
2 |
Subway cut/cover |
$ 144.1 |
|
3 |
Subway mined tunnel |
$ 90.3 |
|
4 |
Track work installation |
$ 5.1 |
|
5 |
Construct stations |
$ 121.2 |
|
6 |
Install traction power system |
$ 6.3 |
|
7 |
Signaling system |
$ 9.8 |
|
8 |
Communications system |
$ 3.4 |
|
Total |