Table 4: Project Cost Tracking Schedule, Escalated Dollars (Millions)
|
No. |
Descrition |
Baseline Budget |
Contract Award |
Approved Changes |
Current Contract |
Forecasted Changes |
Contract to be Awarded |
Current Budget Forecast |
Expenditures To-Date |
|---|---|---|---|---|---|---|---|---|---|
|
Preliminary engineering |
$10.3 |
$10.3 |
$ - |
$10.3 |
$ - |
$10.3 |
$10.3 |
||
|
Final eng. And mgmnt |
$43.8 |
$42.5 |
$ - |
$42.5 |
$ - |
$42.5 |
$5.5 |
||
|
Real estate |
$7.6 |
$7.8 |
$0.4 |
$8.2 |
$ - |
$ 8.2 |
$4.9 |
||
|
Vehicles |
$23.3 |
$22.5 |
$ - |
$22.5 |
$ - |
$22.5 |
$ - |
||
|
Construction Contracts |
|||||||||
|
1 |
Mintenance facility |
$34.7 |
$32.4 |
$(0.5) |
$31.9 |
$ - |
$31.9 |
$ - |
|
|
2 |
Subway cut/cover |
$144.1 |
$148.8 |
$ - |
$148.8 |
$ - |
$148.8 |
$5.2 |
|
|
3 |
Subway mined tunnel |
$90.3 |
$94.2 |
$ - |
$94.2 |
$ - |
$94.2 |
$1.5 |
|
|
4 |
Trackwork installation |
$5.1 |
$ - |
$ - |
$ 5.1 |
$5.1 |
$ - |
||
|
5 |
Construct stations |
$121.2 |
|
$ - |
$ - |
$(2.5) |
$121.2 |
$118.7 |
$ - |
|
6 |
Traction power system |
$6.3 |
$ - |
$ - |
$6.3 |
$6.3 |
$ - |
||
|
7 |
Signalling system |
$9.8 |
$ - |
$ - |
$9.8 |
$9.8 |
$ - |
||
|
8 |
Communications system |
$3.4 |
$ - |
$ - |
$(0.2) |
$3.4 |
$3.4 |
$ - |
|
|
Total |
$499.8 |
$358.5 |
$(0.1) |
$358.4 |
$(2.7) |
$145.7 |
$501.4 |
$27.4 |