| No. |
Element |
FTA Circular 4220.1E Paragraph No. |
Grantee Procurement Policy/Procedure Reference |
| 1) |
Written Standards of Conduct |
7.c. |
|
| 2) |
Contract Administration System |
7.b. |
|
| 3) |
Written Protest Procedures |
7.l. |
|
| 4) |
Prequalification System |
8.d. |
|
| 5) |
System for Ensuring Most Efficient and Economic Purchase |
7.d. |
|
| 6) |
Procurement Policies and Procedures |
7.a. |
|
| 7) |
Independent Cost Estimate |
10. |
|
| 8) |
A&E Geographic Preference |
8.b. |
|
| 9) |
Unreasonable Qualification Requirements |
8.a.(1) |
|
| 10) |
Unnecessary Experience and Excessive Bonding |
8.a.(2) |
|
| 11) |
Organizational Conflict of Interest |
8.a.(5) |
|
| 12) |
Arbitrary Action |
8.a.(7) |
|
| 13) |
Brand Name Restrictions |
8.a.(6) and 8.c. |
|
| 14) |
Geographic Preferences |
8.b. |
|
| 15) |
Contract Period of Performance Limitation |
7.m. |
|
| 16) |
Written Procurement Selection Procedures |
8.c. |
|
| 17) |
Solicitation Prequalification Criteria |
8.d. |
|
| 18) |
Award to Responsible Contractors |
7.h. |
|
| 19) |
Sound and Complete Agreement |
15. |
|
| 20) |
No Splitting [Micro-purchase] |
9.a. |
|
| 21) |
Fair and Reasonable Price Determination [Micro-purchase] |
9.a. |
|
| 22) |
Micro-Purchase Davis Bacon |
9.a. |
|
| 23) |
Price Quotations [Small Purchase] |
9.b. |
|
| 24) |
Clear, Accurate, and Complete Specification |
8.c.(1), 9.c.(2)(b) & 9.c.(1)(a) |
|
| 25) |
Adequate Competition - Two or More Competitors |
9.c.(1)(b) |
|
| 26) |
Firm Fixed Price [Sealed Bid] |
9.c.(1)(c) |
|
| 27) |
Selection on Price [Sealed Bid] |
9.c.(1)(c) |
|
| 28) |
Discussions Unnecessary [Sealed Bid] |
9.c.(1)(d) |
|
| 29) |
Advertised/Publicized |
9.c. & d. |
|
| 30) |
Adequate Solicitation |
9.c.(2)(a) & 9.d.(2) |
|
| 31) |
Sufficient Bid Time [Sealed Bid] |
9.c.(2)(a) |
|
| 32) |
Bid Opening [Sealed Bid] |
9.c.(2)(c) |
|
| 33) |
Responsiveness [Sealed Bid] |
9.c.(2)(d) |
|
| 34) |
Lowest Price [Sealed Bid] |
9.c.(2)(d) |
|
| 35) |
Rejecting Bids [Sealed Bid] |
9.c.(2)(e) |
|
| 36) |
Evaluation [RFP] |
9.d.(1) & 9.d.(3) |
|
| 37) |
Price and Other Factors [RFP] |
9.d.(4) |
|
| 38) |
Sole Source if Other Award is Infeasible |
9.h. |
|
| 39) |
Cost Analysis Required [Sole Source] |
9.h.(2) |
|
| 40) |
Evaluation of Options |
9.i.(1) |
|
| 41) |
Cost or Price Analysis |
10. |
|
| 42) |
Written Record of Procurement History |
7.i. |
|
| 43) |
Exercise of Options |
9.i.(2) |
|
| 44) |
Out of Scope Changes |
9.h. |
|
| 45) |
Advance Payments |
12.a. |
|
| 46) |
Progress Payments |
12.b. |
|
| 47) |
Time and Materials Contracts |
7.j. |
|
| 48) |
Cost Plus Percentage of Cost |
10.e. |
|
| 49) |
Liquidated Damages Provisions |
13. |
|
| 50) |
Qualifications Exclude Price [A&E] |
9.e. |
|
| 51) |
Serial Price Negotiations [A&E] |
9.e. |
|
| 52) |
Bid Security [Construction over $100,000] |
11.a. |
|
| 53) |
Performance Security [Construction over $100,000] |
11.b. |
|
| 54) |
Payment Security [Construction over $100,000] |
11.c. |
|